Public Works Committee Discusses Water Resiliency Projects, Tolovana ADA Ramp Options, and Wastewater Legal Issues

This summary was generated by AI, which occasionally makes mistakes, especially spelling names. Not an official record, for informational purposes only.

Water Resiliency Projects Update

Karen La Bonte, the Public Works Director, provided an update on the city's water resiliency projects. Phase one of the project is complete, and training for the ShakeAlert valves is being set up. Phase two is expected to resume in May, with the focus on bringing water from the springs to the public works yard. The city has successfully secured an easement with the conference center for phase three, and the bid for this phase should be issued in the coming months. The transmission backbone along Highway 101 is approximately 70% complete, with ongoing engineering work.